[-] atheken@programming.dev 8 points 1 year ago* (last edited 1 year ago)

Breaking larger tasks down effectively removes uncertainty.

My general rule of thumb in planning is that any task that is estimated for longer than 1 day should be broken up.

Longer than one day communicates that the person doing the estimate knows it’s a large task, but not super clear about the details. It also puts a boundary around how long someone waits before trying to re-scope:

A task that was expected to take one week, but ends up going 2x is a slide of a week, but a task that is estimated at one day but takes 3x before re-scope is a loss of 2 days.

You can pick up one or two days, but probably not one or two weeks.

this post was submitted on 29 Jul 2023
132 points (97.8% liked)

Programming

17314 readers
72 users here now

Welcome to the main community in programming.dev! Feel free to post anything relating to programming here!

Cross posting is strongly encouraged in the instance. If you feel your post or another person's post makes sense in another community cross post into it.

Hope you enjoy the instance!

Rules

Rules

  • Follow the programming.dev instance rules
  • Keep content related to programming in some way
  • If you're posting long videos try to add in some form of tldr for those who don't want to watch videos

Wormhole

Follow the wormhole through a path of communities !webdev@programming.dev



founded 1 year ago
MODERATORS