155
Canada vows to triple nuclear power production by 2050 | CTV
(london.ctvnews.ca)
What's going on Canada?
🍁 Meta
🗺️ Provinces / Territories
🏙️ Cities / Local Communities
🏒 Sports
Hockey
Football (NFL)
unknown
Football (CFL)
unknown
Baseball
unknown
Basketball
unknown
Soccer
unknown
💻 Universities
💵 Finance / Shopping
🗣️ Politics
🍁 Social and Culture
Reminder that the rules for lemmy.ca also apply here. See the sidebar on the homepage:
The last power plant I worked on was Chinook generating station near Swift Current, a 350MW combined cycle plant for SaskPower. At $605M is was $75M under budget, you will never hear that on a nuclear project.
The various wind installations are typically fairly close to budget and schedule as well. Hydro is problematic, and that does show in cost overruns, because it is very difficult to predict the geotechnical situation for a given site until excavation starts. Given the stress on the structures, even small differences accumulate rapidly.
The worst thermal plant projects are consistently nuclear.
The refurbishment of Lepreau was supposed to cost $1.5B and take 18 months, it ended up taking $2.5B and just under 4 years to complete.
Flammanville-3 started construction in 2007 was supposed to be operational in 2012. They're now estimating it will complete commissioning in 2024. Costs have gone from €3.3B to €20B+.
Olkiluoto-3 started construction in 2005, was supposed to be operational in 2010, but only completed commissioning in 2022. Costs went from €3B to €11B, the not to exceed amount in the contract.
Hinkley Point C started about 2016, has been pushed back to 2028 and costs have gone from £16B to an estimated £32B.
Vogtle has been covered, but the V.C Summer plant was no better. Initial estimate was $9B, but the project was cancelled while under construction when the estimated total was projected to exceed $23B.
The numbers for nuclear sound absolutely fantastic for whoever wins the contract. 🤔